Monday, November 19, 2012

Exterior finishes

The driveway has been poured (though it's under blankets due to the cool weather), the siding is up, and the gabions are installed: almost there!
Entry view: the door is unveiled at last!

Feels good as an architect to see the building appearing as drawn and imagined. This goes to show how important a good drawing is. And while that's important for the visible design, thorough documentation is even more critical when it comes to airtightness and thermal-bridge-free detailing. 

That plug for our profession out of the way, I'd like to say a few things about the exterior design and finishes.  Having served on Oak Park's Historic Preservation Commission for 5 years, I became more sensitive to the massing, roof overhangs, and window-to-wall ratios typical of late 19thc./early 20thc. architecture: before the time of clean and powerful air conditioning and heating.  Studying Passive Houses, it became apparent that a similar principle was at work: the shape, orientation, and number/placement of windows powerfully affect the energy balance of a building.  This doesn't mean that Passive Houses need to look "traditional", but they do share a continuity of design thought with traditional buildings.  I like that. 

The mass of this house was intended to have a traditional compact rectangular form and gabled roof; siding detailing of the thick walls offered design opportunities. First, we provided overhangs for the old-fashioned reason: they really do protect walls and windows.  On the walls we also provided intermediate trims with drip flashings to get water away from the wall and windows.  We chose LP SmartSide as the siding finish.  Like other siding products (fiber cement), it has a really long finish warranty (LP offers a 50 year transferable warranty!). But unlike fiber cement, it is much stronger, lighter, and impact resistant, and it is made entirely of wood (SFI certified fast-growing lumber specifically for OSB and siding).  Since they pulp the lumber, they use the entire tree, and do not add formaldehyde in the manufacturing process.  SmartSide comes in smooth and rough finishes, so we took the opportunity to break down the mass and create interest by contrasting alternating bands.  The exposures are 11" (rough) and 5" (smooth), which repeat the 16" coursing of the ICF blocks inside the walls. 

The basement windows needed areaways with retaining walls.  Traditionally these are of concrete, but realizing we had a lot of brick left over from the previous house, we decided to use the brick to fill wire baskets (gabions) which could operate as retaining walls merely by virtue of their mass: a simple recycling move that saved money and embodied energy. 
South basement window

Another thing about the gabions: they're a lot nicer to look at from the inside that concrete:
Front basement bedroom window
Dig Right In, eco-landscape firm out of Brookfield, is contracted to provide the landscape design and installation, which is scheduled in the next week or two. 

Monday, October 1, 2012

Pictures, Sept. 26

Here are some updated pictures I took for my presentation at the Passive House Conference last weekend in Denver.  More soon!
front--brick just installed

living/dining space looking east to stair

from stair to west (back of house)

exterior rear of house

You may be wondering why the drywall is blue--it's a new product from Certainteed that captures and sequesters aldehydes and VOCs, so it will contribute even more to the healthy interior.

Most of the Passive House-specific items are installed, and the next few months will focus on finishes and fixtures.  Stay tuned!

Thursday, September 13, 2012

Blower door did not suck

There are too many bad jokes to be made about blower doors...I couldn't resist.

This is just a very quick post to announce the our PHIUS+ rater, Andy Scott of Energistics, came to the site this week and performed the preliminary blower door test.  As soon as we turned the fan on we started smelling sewer gas (plumbing is just at rough, so no traps installed.  So we plugged them with rags and fiberglass (not exactly airtight, but kept the stink down and gave us a more accurate reading.  Andy didn't have a "C ring" to be able to get below 300cfm, so Brandon got one from his truck...
...here he is wearing it like a hat...
...and we got the reading: 240cfm, which translates to about 0.38ACH50, well below the 0.6 Passive House threshold, and we will be able to tighten a bit more with the plumbing.  A big congratulations are in order for Brandon and Eric for sealing the windows and doors so well...
tiny crack at the miter--but needs to be there to allow glass to be replaced

great seals on the doors and windows
...as well as the few penetrations through the ceiling.
gaskets were perfect
I'll say it again: this is a great team!




Tuesday, September 11, 2012

Heating and cooling the Passive House

One of the main qualities of a Passive House building is that the mechanical loads are so reduced that you only need a tiny system for heating and cooling.  Even for this relatively big house, there is no conventional furnace/AC small enough that it wouldn't be way oversized, and therefore short-cycle.

Our heating and cooling is handled with the new stars on the efficiency stage, mini-split (or ductless) heat pumps.  This is a rapidly expanding field that bears little resemblance to the heat pumps of the 1970's and '80's.  Heat pumps exchange heat similarly to the way air conditioners or refrigerators do, but can work in both directions to provide both heating and cooling.  The early units got a bad rap in the 80's for being inefficient at supplying heat below 30F or so, but the new Mitsubishi units we're using supply their full nominal heating output at 5F and continue to operate efficiently down to -13F.  With a SEER rating of 26  and heating Coefficient of Performance over 3, the ductless heat pump is a terrific unit. But they gain even more efficiency from the fact that they can modulate down to run at partial load--so they will run on a very low setting if you just need a little heating or cooling, which is way more efficient than coming on, blowing hard, and shutting off. Another benefit in cooling mode is that the unit can dehumidify continuously, even at low levels of output.  Aside from being a more comfortable way to get your space conditioning, it is also nearly silent.  You literally can't hear these units unless you get your ear right up on top of them.

They have an outdoor unit that looks like a small, upright A/C condenser, and a wall unit with a fan that provides conditioning.  Here's the rough installation of the units:
Master Bedroom


Living Room
Mitsubishi and others also have units that can be ducted, but we didn't want (or need) to get into that.  One of the other qualities of the superinsulated Passive House is that, since the walls lose heat so slowly, you just don't need to duct heat around to provide even temperature in the house.  The ventilation system helps the air circulate, and convection and vapor pressure migration take care of the rest.  Super comfort, Passive style.

Ventilation for the Passive House

One of the qualities of a Passive House is that the construction is nearly airtight., so to allow the house to "breathe" we use an energy-recovery-ventilator (or heat-recovery ventilator).  Yes, houses need to "breathe", or more accurately, people inside houses need fresh air, but the problems with leaky construction are at least threefold: 1.) you don't know if the leaks are getting fresh air where you need it (like in the bedrooms), 2.) as it leaks in, the air picks up contaminants and can cause condensation, mold, and deterioration of the structure; and 3.) you don't know the rate of "leaking", so combustion gases, moisture, etc. may not be getting cleared out of your house.  My analogy is that we want the beast to breathe through its nostrils, not through gaps in its skin.

Like all Passive Houses, ours has a balanced ventilation system (same amount of supply and exhaust) that runs continuously. It has an extremely efficient fan, and recaptures about 85% of the outgoing heat, so it is a low-energy way of providing great indoor quality.  The system extracts air from the kitchen, bathrooms, laundry, basically any place that makes moisture and odors, and supplies fresh air to bedrooms and other living spaces.  Imagine getting fresh air continuously as you sleep...you wake more refreshed, having been breathing air that was cleaned of pollen and molds by the (MERV 7/8) filter. 
Zehnder, beginning of installation

Our system is a Zehnder ComfoAir 550. Zehnder not only has great heat recovery technology, but they have also developed a suite of products that make sizing, installation, and commissioning (getting air flow right) a breeze.  The small flexible ducts clip into supply and exhaust manifolds, and into supply and return diffusers, which have fittings to adjust flow rates.
Zehnder with ductwork connected to supply and exhaust manifolds
 These ducts are flexible and fit in a standard 2x4 cavity, so are quite easy to work into the construction site (though I recommend a riser for ducts running from the manifolds to another floor).  One reason each diffuser is individually ducted is that precise airflow can be guaranteed at each location. Commissioning consists of testing each diffuser at the end of installation and adjusting the unit's fans and the diffusers themselves to ensure design flow rates.  Once set, it typically doesn't take maintenance to maintain the flow rates; all that needs to be done is occasional cleaning of the filters.  Clean, fresh, healthy air, 24/7.

Thursday, September 6, 2012

Passive House window installation in ICF

We learned a lot about windows...hence this post to pass it on.
First, we priced a number of European windows that would work for our demands: we needed glass at about U=.09, frames at about U=.15, solar heat gain coefficient of .5, and insulating spacers.  We learned that the UPVC windows (Intus, Unilux Isostar, Zola) fit the bill at the lowest price.  Great prices, actually, as in, competitive with good US wood/clad windows (I recently heard around $34/s.f. for UPVC units).  Our clients preferred aluminum clad wood, though, and we wound up choosing Zola's Thermo line. Their performance was great, and their price beat the competition easily. They're made in Poland with German Roto hardware. Florian Speier, the architect who founded Zola, helped develop the THERM protocol for determining installation thermal bridge values, so he's a good resource to the Passive House Consultant as well. By the way, I'm not going to name "the competition" here, because the pricing we got might not be indicative of where their products stand today, or with other project specifics, and I don't want to prejudice anyone unfairly.

A few logistical items to note:
- Shipping from Europe didn't allow for an exact delivery date: plan for flexibility.
- The shipping container was packed excellently for safe travel of the windows, but not for jobsite storage (the windows weren't individually crated).
Inside the crate

- You typically have to pay to hold a shipping container on site, so either unload the windows to a safe location (for us not easy on the small job site) or install them right away.
- These are beautiful, finished, furniture-like pieces of equipment, so they need protection for the duration of construction.
- Powder-coated Zola screens were expensive--we're going to have them made locally instead.

For installation we had two options: screw through the jambs into the bucks, or use metal clips that slotted into the jambs.  Since we had solid concrete behind the jambs, and didn't have close enough tolerance on all the shim spaces, we chose to use the clips.

Clip is just below green tape, which is covering buck anchor
That meant we had another blip to deal with in our airtight layer, but by this time we were so Siga-happy we didn't worry about it.  As you can see, we used the Siga Corvum to tape the jamb to the buck (Corvum is pre-folded with two peel-away strips on the back, made for corner air sealing), and the Wigluv to cover the clip-blips.

Air sealed window. Note: interior overinsulation will cover tape.
Initially we were concerned about the airtightness strategy at the windows, but having done it, it's actually pretty easy and entirely visible and accessible, making it easy to fix if there are any weak points.

The weathertightness on the outside was handled with more traditional flexible flashing. Here's Brandon Weiss, the GC, explaining how that was done:

 And here's an exterior view, with a window awaiting the overinsulation on which to tape off the flexible sill flashing:
Exterior: west family room window

Man, I should offer CEU credits for this blog post!  Hope it's helpful to those out there detailing.  Your comments are welcome...this is a learning experience for us.

Friday, August 3, 2012

Roof is raised

Biltmore continues to move at their good and steady pace.  The roof went on a few weeks ago, followed quickly by interior framing.  But first, the ceiling air barrier was installed.  Every airtight house (and Passive Houses are the ultimate airtight houses!) need to have a continuous air barrier.  Our ICF walls are pretty straightforward air barriers, but each penetration (doors, windows, ERV ducts, etc.) and change of plane (wall to ceiling and slab) need careful attention to detail.  I'll cover windows in an upcoming post, but in this post would like to show how we dealt with the wall to ceiling transition.
Taking shape: the roof is on!

We laid a sheet of plastic over the top of the wall and under the wood top plate on which the roof trusses sit.  This sheet is taped to the exterior face of the ICF form and to the plywood diaphragm that we attached to the bottom of the trusses.  All the seams in the plywood diaphragm will be taped with Siga tape, and plumbing and electrical penetrations will be sealed with Roflex gaskets we got from 475 High Performance Building Supply.  It's great having these suppliers in the US!
This plastic gets taped to interior ceiling and exterior face of ICF

Instead of holding up interior framing until the entire ceiling air barrier was taped, the builders simply taped seams that were to be crossed by interior walls.
Air sealing at ceiling/wall and window/wall
Look closely and you'll see the stitches of tape where walls pass under air barrier seams

And speaking of air barriers--this is how we dealt with the slab: our radon barrier is our air barrier, so we used Stego Wrap since it's tough; utility penetrations are taped off to it, and it in turn is taped to the inside face of the ICF form.
StegoWrap radon/air barrier taped to interior face of ICF
 Stay tuned--windows will all be in this week, so the next post will soon follow!

Tuesday, June 5, 2012

ICFs going up

Biltmore Insulated Concrete is erecting the Logix ICF walls and installing bucks for window openings:
view from street

airtightness tape at buck corners
The first concrete pour is scheduled for tomorrow.

Monday, May 28, 2012

Renderings of River Forest house

Here are two exterior views of the RF house:
F R O N T   E N T R Y
S O U T H W E S T


Monday, May 21, 2012

Construction begins

May 18, 2012

Eric Barton of Biltmore Insulated Concrete and Brandon Weiss of Weiss Building and Development are the builders, and top-notch builders they are--both Graduate Master Builders, Brandon is BPI certified, Eric is a Certified Passive House Consultant...couldn't hope for a better team.  They started by delivering the ICF forms and salvaging windows and framing lumber in advance of demolition.
...this will be a house soon...
 Excavation will follow demo, and concrete will flow soon.
May 21, 2012
Stay tuned!



Thursday, May 10, 2012

Why certification? What PHIUS+ is doing for us

The River Forest house has been submitted to PHIUS for the PHIUS+ certification process, and I am occasionally asked what the incentive is--what are we getting for the $2700-ish in fees?  The answer is twofold: 1.) expert review of the design; and 2.) third-party verification of the construction.

I recently received comments from the first review, and look on it as a kind of finishing school for PHPP, since it's being done by one of the most seasoned PHPP users in the country. I had missed some major opportunities for summer and night ventilation as well as interior shading, all of which drastically reduced my cooling loads, and therefore my Primary Energy.  There is also an interesting issue with houses above PHPP's expected floor-area-per-person range: internal heat gains, which are significant in such super-insulated, airtight houses, get lower the more floor area per person.  So we had to take a close look at appliance loads and expected plug loads.  As covered in the "Klingenblog," US houses are proving to be higher in electrical use than PHPP predicts, affecting internal heat gains as well, so that is an important item to accurately predict: how many TVs? Will there be a server running continuously?  Her coverage of Blake Bilyeu's house in Oregon was an eye-opener regarding electrical use.  And finally, there is always the benefit of peer review--I had missed two windows and some shading factors, and having someone looking over your shoulder makes you catch those.

The project is back to PHIUS, and we hope to get our pre-certification notice soon.  Construction is starting next week, and the ICF forms have been delivered.  Once construction is underway, the next phase of the PHIUS+ program begins, in which Andy Scott of Energistics will show up on site for QA/QC, including inspecting the insulation installation and performing blower door test.  In short, PHIUS+ is providing us with certainty that the house we have designed is accurately modeled, and that construction quality is assured.

Update: we're the happy recipients of pre-certification:
As Kat said in CPHC training, going through certification way is the quickest path to really knowing your away around PHPP.  I'd love to get my teeth into a commercial project next!

Monday, February 6, 2012

New project: ICF Passive House in River Forest

I'm excited to share that I'm designing a new house (planned to be certified by PHIUS) for a wonderful young family, with a great team of builders.  The owners asked for a home that would not only be super-energy-efficient, but extremely strong as well.  They want a house that will last, and that will offer them psychological and physical comfort.  Working with clients like this makes being an architect so rewarding.

When they said they wanted a very strong house (in fact they asked for concrete), I thought of my friend and associate Eric Barton of Biltmore Insulated Concrete, an ICF expert that took the Passive House Consultant Training with me (and recently passed his exams, congrats Eric).  I also turned to Brandon Weiss of Weiss Building and Development, an award-winning green builder who focuses on building science and efficiency.  Brandon will be the GC, Eric will handle the ICFs and most of the thermal shell.  Having the complete team working toward a common vision is essential, so we're in a good position.

South wall
Schematic design is complete, and we plan to wrap up Design Development at the end of the week.  Initial Annual Heating Demand is coming in under 4kBTU/s.f. yr., including most thermal bridging accounted for; when we get the documents together at the end of the week, the project will go off to PHIUS for pre-certification.  After that, Andy Scott of Energistics will take over the rating part of the certification process. I'm going to cover the PHIUS+ process in some detail so those curious how it works can learn.  Here are a few renderings of the in-process design.

Entry